Window replacement permits in Shoreline: fees, timeline & requirements (2026)

Everything you need to know about pulling a window replacement permit in Shoreline, Washington — when one is required, what it costs, how long review takes, what documents are required, and which inspections you can expect. Cited to Shoreline Planning & Community Development.

Look up your Shoreline address

Free lookup, no account needed — the office that issues the permit at your address, cited to Shoreline's source.

Permit required?
Permit if: a new or resized opening · structural elements revised · an escape opening reduced in size.
Permit fee
About $447 for an $8,000 project, when a permit is needed
Review timeline
Not published by the city

When does a window replacement need a permit in Shoreline?

Replacing windows of the same size in the same location most likely does not need a permit. Moving or enlarging a window opening requires a building permit. New glazing must meet 2021 WSEC R402 U-factor/SHGC.

In the source's own words

“If you are just repairing or replacing fixtures in the same location or replacing windows (same size, same location), you will most likely not need a permit.”
Source ↗verified 2026-05-17

Required submittals

  • Permit Application and Critical Area Worksheet (Residential Interior Remodel checklist — Required Documents > Applications)
  • Submittal Fee per City fee schedule (Residential Interior Remodel checklist — Required Documents > Submittal Fee)
  • Construction Documents per Construction Documents handout (Residential Interior Remodel checklist — Required Documents > Construction Documents)
  • Accessory Dwelling Unit (ADU) Worksheet — required when creating a new ADU or changing an existing ADU (Residential Interior Remodel checklist — Additional Documents > ADU Worksheet)
  • Waste Diversion Plan and Salvage Assessment — required for construction/alterations exceeding 1,000 sq ft gross floor area, or when demolition is proposed (Residential Interior Remodel checklist — Additional Documents > Waste Diversion)
  • Water Availability Certificate — required when adding new plumbing fixtures and property is served by North City Water District (Residential Interior Remodel checklist — Additional Documents > Water Availability Certificate)

Inspection sequence

  1. Rough-opening inspection (if structural)
  2. Final

Contractor specialties needed

General contractor

Who can do this work in Shoreline?

Kolmo Construction is a licensed Washington general contractor — KOLMOL*753JS, active through April 10, 2027, bonded and insured — working throughout Shoreline and King County. Kolmo prepares the drawings and submittals, files the window replacement permit with Shoreline Planning & Community Development, carries the project through review and inspections, and performs the construction. Call (206) 410-5100 for a Shoreline window replacement quote.

Notes & caveats

WSEC R402.4: replacement windows must meet U-factor ≤0.30 (climate zone 4C/5B applicable to most WA). Egress sleeping rooms must retain compliant opening (R310).

Window replacement permit fee estimate in Shoreline

Worked example for an $8,000 window replacement project (building permit). Your actual fee scales with project valuation.

Building permit fee$267
Plan review$173.55
WA state surcharge$6.50
Estimated total$447.05

Where a window replacement needs a building permit in Shoreline, it is priced on the value of the work, as supplied by the applicant or contractor: $267 up to $16,000, $75 for the first $2,000 plus $14 for each $1,000 more up to $25,000, and $397 for the first $25,000 plus $11 for each $1,000 more up to $50,000. Plan review is 65% of that fee, plus the $6.50 state building code fee. A 4% technology surcharge is added to the City's permit fees (SMC FEE.010). Apply electronically via eTRAKiT (shorelinewa.gov/government/departments/planning-community-development/permit-center-remote-services/register-for-a-professional-etrakit-account). Computed from Shoreline's adopted fee schedule · source ↗. Land use, fire and engineering review, intake, impact and utility fees, where they apply, are charged separately.

How to apply yourself

  1. 1. Check who issues the permit. Run an address lookup for your window replacement in Shoreline — we'll confirm which office issues the permit at that address.
  2. 2. Assemble submittals: the 6 documents under Required submittals above.
  3. 3. Submit through the city portal: Shoreline Planning & Community Development ↗
  4. 4. Track review. Respond to reviewer comments promptly.
  5. 5. Pay issuance fees (about $447 for an $8,000 project) and pick up the permit. Inspection card travels with the job.

Or have Kolmo do it

Kolmo prepares the drawings and submittals, files with Shoreline Planning & Community Development, handles reviewer comments, and builds the project.

(206) 410-5100

Licensed WA general contractor KOLMOL*753JS · bonded & insured

Window replacement permits in Shoreline — FAQ

When does a window replacement need a permit in Shoreline?

Replacing windows of the same size in the same location most likely does not need a permit. Moving or enlarging a window opening requires a building permit. New glazing must meet 2021 WSEC R402 U-factor/SHGC.

How much does a window replacement permit cost in Shoreline?

For a $8,000 window replacement project, the estimated Shoreline permit fee is about $447.05 (building fee $267 + plan review $173.55 + surcharges) from Shoreline's adopted fee schedule. Land use, fire and engineering review, intake, impact and utility fees, where they apply, are charged separately.