TL;DR
Seattle allows two ADUs per lot, up to 1,000 sq ft (1,200 with three bedrooms), with no parking or owner-occupancy rule. DADU permits took a median 109 days.
Figures by Kolmo Construction, a licensed Seattle-area general contractor — (206) 410-5100 · free estimates.
Table of Contents
- Quick summary and key takeaways
- What counts as an ADU in Seattle
- Seattle ADU rules at a glance
- Can I build two ADUs on my Seattle property?
- How big can an ADU be in Seattle?
- The lot's floor area limit rises as you add homes
- Where can a backyard cottage go on my lot?
- Do I have to live on the property if I build an ADU?
- Does Seattle require parking for an ADU?
- Can I turn my garage or basement into an ADU?
- What SDCI checks on a conversion
- How long does an ADU permit take in Seattle?
- Pre-approved plans are faster, but not 2 to 6 weeks
- What sends ADU plans back
- What permits does an ADU need?
- What the SDCI permit costs
- Past two ADUs: middle housing
- Why you'll read different rules online
- Red flags when you hire for an ADU
- Before you apply: a checklist
- Sources, dates and how to cite this page
Most ADU questions we get start with the rules, not the price. Can my lot take a backyard cottage? How big can it be? Do I have to live there? How long will the city take? This guide answers those from Seattle's land use code as it stands going into 2027, and from the city's own record of the ADU permits it issued over the last 12 months.
Kolmo Construction (WA Lic# KOLMOL*753JS) builds attached and detached ADUs and garage and basement conversions around Seattle. For what an ADU costs, see our Seattle ADU cost guide. This page covers what the code allows and how the permit goes.
Quick summary and key takeaways
- A Seattle lot can have two ADUs: two attached, two detached, or one of each.
- An ADU can be up to 1,000 square feet, or 1,200 square feet with three or more bedrooms. Underground floors and up to 250 square feet of attached garage don't count.
- No parking is required, the city can't require you to live on the property, and an ADU can be sold as a condominium.
- A detached ADU needs a 5-foot rear setback (none on an alley) and 5 feet of space from the house.
- Over the last 12 months, Seattle issued detached ADU permits in a median of 109 days. Pre-approved plans took a median of 86 days in 2025, well past the 2 to 6 weeks the city quotes.
What counts as an ADU in Seattle
An accessory dwelling unit is a second, smaller home on the same lot as a house, with its own living, sleeping, kitchen and bathroom space and a lockable entrance. Seattle uses two names:
- An attached ADU (AADU) is inside or attached to the house: a basement suite, an attic unit, a converted attached garage or a new addition.
- A detached ADU (DADU) is a separate building: a backyard cottage, a unit over a detached garage, or a converted detached garage.
A tiny house on a foundation counts as a DADU. A tiny house on wheels does not. SDCI treats it like a camper, and you can't live in one on a Seattle lot.
ADUs are allowed in every zone that allows housing (SMC 23.42.022.A). Most Seattle houses sit in the neighborhood residential zones (NR1, NR2 and NR3), so the setbacks and heights below are the NR figures.
Seattle ADU rules at a glance
- How many: two ADUs per lot, attached, detached or stacked (SMC 23.42.022.C and D).
- Size: 1,000 square feet of gross floor area, or 1,200 with three or more bedrooms (23.42.022.G). Underground stories, up to 250 square feet of attached garage and up to 35 square feet of bike storage don't count.
- Height: the same limit as the house, 32 feet in NR zones (23.42.022.E and 23.44.070).
- Rear setback: 5 feet for an ADU, and none where the lot backs onto an alley (23.44.090).
- Front and side setbacks: the house's, which in NR zones means 15 feet in front on a lot with one or two homes, and side setbacks of 5 feet on average and 3 feet at the narrowest.
- Space from the house: 5 feet, more if a driveway runs between them (23.44.100).
- Lot coverage: 50% of the lot for all buildings together (23.44.080).
- Parking: none required (23.42.022.I).
- Owner on site: can't be required (RCW 36.70A.681).
- Minimum lot size: no separate minimum for an ADU.
- Selling the unit: allowed as a condominium (23.42.022.K).
Can I build two ADUs on my Seattle property?
Yes. Seattle allows up to two accessory dwelling units on a lot (SMC 23.42.022.C), and state law requires every Washington city to allow any mix of them: one attached and one detached, two attached, or two detached in one or two buildings (RCW 36.70A.681). The two units count toward the lot's density along with the house (23.42.022.J), which raises the lot's floor area limit and matters if you plan more homes later. The mix matters for the building code. Two attached ADUs inside an existing house make it a three-unit building, and SDCI then reviews it as an apartment building under the Seattle Existing Building Code, where a substantial alteration brings sprinkler, seismic, egress and energy requirements (SDCI Tip 116A). One attached and one detached unit keeps both buildings under the residential code.
How big can an ADU be in Seattle?
An ADU with up to two bedrooms can have 1,000 square feet of gross floor area, and one with three or more bedrooms can have 1,200 (SMC 23.42.022.G). Three kinds of space don't count against that cap: stories that are underground, up to 250 square feet of an attached garage, and up to 35 square feet of long-term bike storage. An attached ADU in a part of the house that already stood on July 23, 2023 has no size cap at all, so a large existing basement can become one unit without walling part of it off.
The lot's floor area limit rises as you add homes
Separate from the ADU cap, every NR lot has a floor area ratio (FAR) limit on all its buildings together, and the limit goes up with the number of homes on the lot, ADUs included (SMC 23.44.050). On a 5,000 square foot lot:
- A house alone (one home per 5,000 sq ft): FAR 0.6, or 3,000 square feet.
- A house and one ADU (one home per 2,500 sq ft): FAR 0.8, or 4,000 square feet.
- A house and two ADUs (one home per 1,667 sq ft): FAR 1.0, or 5,000 square feet.
Underground floors, and any part of a story no more than 4 feet above grade, don't count toward FAR. A lot under 5,000 square feet always gets at least 2,500 square feet.
Where can a backyard cottage go on my lot?
A detached ADU needs a 5-foot rear setback, or none where the rear lot line is an alley (SMC 23.44.090). Its front and side setbacks are the house's: in NR zones, a side setback of 5 feet on average and 3 feet at the narrowest, and a front setback of 15 feet on a lot with one or two homes. It has to stand at least 5 feet from the house, and farther if a driveway or parking aisle runs between them (23.44.100). All buildings together can cover half the lot (23.44.080), and the cottage can be as tall as the house is allowed to be, 32 feet in NR zones (23.42.022.E and 23.44.070). Many lots in older grid neighborhoods like Ballard, Wallingford and Columbia City back onto an alley, which takes the rear setback to zero.
On a lot under 5,000 square feet inside a frequent transit service area, the house's own setbacks shrink to 5 feet at the rear and 3 feet at the sides.
Do I have to live on the property if I build an ADU?
No. State law bars any Washington city from requiring the owner to live in the ADU or in the house (RCW 36.70A.681), so you can rent both. If an earlier owner recorded Seattle's old owner-occupancy covenant against the title, SDCI has a form to release it. An ADU can also be sold on its own as a condominium: Seattle's code can't be read to block that sale (SMC 23.42.022.K), though setting up a condominium takes its own legal work.
Does Seattle require parking for an ADU?
No. Seattle requires no off-street parking for an accessory dwelling unit (SMC 23.42.022.I), and SDCI lists parking, street improvements and Mandatory Housing Affordability payments among the standards that don't apply to ADUs. Parking still shows up in plan review, though. On 42% of the detached ADU permits that drew corrections, reviewers asked about parking layout: space size, backing distance, location or EV readiness. If your plans show a parking space, it gets checked like any other.
Can I turn my garage or basement into an ADU?
Yes, and the zoning code goes easier on conversions than on new buildings. A detached garage or shed that stood before July 23, 2023 can become a detached ADU even if it sits inside today's setbacks or puts the lot over its coverage limit, and SDCI can waive other ADU and zone standards to make the conversion work (SMC 23.42.022.H, RCW 36.70A.681). An attached ADU in a part of the house that existed on that date has no size cap. What a conversion doesn't escape is the building code. Turning a garage or basement into a home means meeting the Seattle Energy Code in full, fire and sound separation between the units, and an escape window or door in each bedroom.
What SDCI checks on a conversion
- Each bedroom needs an escape window or door with at least 5.7 square feet of clear opening (5 square feet for a grade-floor opening), at least 24 inches tall and 20 inches wide, with the sill no more than 44 inches above the floor.
- In an existing house, the fire and sound separation between the two units is waived when interconnected smoke alarms run through the whole building (Tip 116A).
- Each unit's heating controls and circuit breakers have to be in that unit or in a shared area, and the ADU needs smoke and carbon monoxide alarms (Tips 116A and 116B).
For what these conversions cost, see our garage conversion cost guide and basement finishing cost guide.
How long does an ADU permit take in Seattle?
Plan on about three and a half months for the permit alone, and up to seven if your plans need several rounds. In the 12 months to November 22, 2026, Seattle issued 233 detached ADU permits that went through plan review. Half were issued within 109 days of application and 80% within 204 days. At the median, 57 of those days sat with the city and 39 with the applicant answering corrections, over three review cycles, and none was issued on the first review. Attached ADUs ran about the same: a median of 107 days across 55 permits.
Pre-approved plans are faster, but not 2 to 6 weeks
SDCI says a pre-approved DADU plan from the city's ADUniverse gallery gets a permit "in most cases" in 2 to 6 weeks. The 30 pre-approved DADU permits Seattle issued in 2025 took a median of 86 days, 80% were issued within 122 days, and every one went through at least one round of corrections. That is still faster than detached ADU permits overall, especially at the slow end (122 days against 204), and the city ran a call for new pre-approved ADU and middle housing designs in 2026.
What sends ADU plans back
From SDCI correction letters on 201 detached ADU permits, the items reviewers raised most often:
- The assigned address on every sheet and the site plan: 89%
- Fire and sound separation, including walls and eaves near property lines: 51%
- Trees and street trees: 46%
- Parking layout: 42%
- Setbacks and space between buildings: 40%
- The lot coverage calculation and diagram: 38%
On 59 attached ADU permits, the top items were ventilation and exhaust fans (66%), heating system sizing and controls (61%), and egress, stairs, guards and headroom (58%).
What permits does an ADU need?
Building an attached or detached ADU takes an SDCI construction permit for an addition or alteration, and legalizing a unit that already exists takes a construction permit to establish its use. Around that main permit sit several others, depending on the job:
- An electrical permit, which SDCI issues in Seattle rather than L&I.
- Plumbing and gas permits from Public Health – Seattle & King County.
- A side sewer permit from Seattle Public Utilities.
- An electrical service change from Seattle City Light, if the house's service can't carry the new unit.
- Shoreline, landmark district or environmentally critical area review, where the lot is in one.
SDCI reports every ADU permit to King County, which bills a sewer treatment capacity charge on the new unit every three months for 15 years, or until you pay off the balance, which you can do early at a discount.
What the SDCI permit costs
Under SDCI's 2026 fee schedule, the building permit and plan review for a detached ADU valued at $250,000 come to about $6,273: a $2,984 permit fee, a $2,984 plan review fee, a 5% technology fee and the state's $6.50 building code fee. Half the permit fee and all of the plan review fee are due at application. Trade permits, drainage review and the side sewer are extra. Our Seattle building permit fee guide walks through the full table. SDCI sets its fees by year, so check its current schedule for 2027.
Past two ADUs: middle housing
Since 2025, Seattle's NR zones allow more homes on a lot than a house and two ADUs. For houses, townhouses and cottages, the density limit is one home per 1,250 square feet of lot, which is four homes on a 5,000 square foot lot. Any lot under 5,000 square feet can have up to four, and a lot under 7,500 square feet within a quarter-mile walk of a major transit stop can have up to six (SMC 23.44.060), as long as it has no wetlands, riparian corridors or steep-slope no-build areas. Only two of those homes can be ADUs. The rest are principal units with their own rules, and that is a different project from adding an ADU.
Why you'll read different rules online
Seattle rewrote its ADU code in 2025 to meet state law (HB 1337) and changed its neighborhood residential zoning to allow middle housing (HB 1110). Much of what's online predates that, including parts of the city's own handouts. SDCI's Tip 116B, last updated August 18, 2023, still lists a 3,200 square foot minimum lot for a backyard cottage and a cap of 40% of the rear yard. Tip 116A, updated November 19, 2026, still says a second ADU must meet green building standards or be income-restricted. None of those rules is in the current code (SMC 23.42.022 and Chapter 23.44), and both Tips say the code controls. When a handout and the code disagree, go by the code and confirm with SDCI.
Red flags when you hire for an ADU
- A builder who says a garage or basement conversion doesn't need a permit. A new dwelling unit always does, and after a complaint SDCI can issue a notice of violation requiring you to legalize an unpermitted unit or remove it.
- A site plan drawn to the old rules above, which can cost you square footage the code now allows.
- A bid that leaves out the side sewer, the electrical service or the King County capacity charge.
- A contractor you can't find on L&I's Verify a Contractor lookup.
Before you apply: a checklist
- Look up your zone and lot size on Kolmo's Seattle ADU permit page.
- Check whether the lot backs onto an alley, or sits in a shoreline, landmark district or environmentally critical area.
- Pick the type: attached, detached, a conversion of an existing building, or a pre-approved plan.
- Measure what the buildings on the lot already cover and their floor area, and run the FAR numbers above.
- Mark the trees on and next to the lot. Tree rules drew corrections on 46% of detached ADU permits.
- Find the size of the electrical service and where the side sewer runs.
- Put the assigned address on every sheet. It is the most common correction SDCI sends.
- Budget the permit fees and the capacity charge, and get a planning number from our Seattle ADU and DADU cost calculator.
- Allow for two or three review cycles. Design over the winter if you want to build in summer.
Questions about your lot? Call Kolmo Construction at (206) 410-5100 or reach us at kolmo.io/contact. To price a project first, start with the cost calculator.
Sources, dates and how to cite this page
The rules on this page are from the Seattle Municipal Code, Section 23.42.022 and Chapter 23.44 as published on Municode (Ordinances 127211 and 127376, read October 2026), SDCI's Accessory Dwelling Unit page and Tips 116A and 116B, and RCW 36.70A.681, all read November 25, 2026. Permit times are from the City of Seattle's issued building permit records (data.seattle.gov dataset 76t5-zqzr), computed November 22, 2026, and the correction shares are from SDCI correction letters. The fee example uses SDCI's 2026 Fee Subtitle. When citing, name the code section or city record as the source and Kolmo Construction, with a link to this page, for the compilation. We re-read the code before each update.
Governor / Managing Member, Kolmo LLC
Pascal handles estimating, contracts, permitting and public-works compliance at Kolmo Construction, and builds the cost model and permit engine behind every figure on this site.
Sources
- Seattle Municipal Code 23.42.022, Accessory dwelling units — accessed 2026-10-11
- Seattle Municipal Code 23.44.090, Setbacks (Neighborhood Residential zones) — accessed 2026-10-11
- Seattle Municipal Code 23.44.050 and 23.44.060, Floor area and maximum density — accessed 2026-10-11
- RCW 36.70A.681, Accessory dwelling units: limitations on local regulation — accessed 2026-11-25
- Seattle Department of Construction and Inspections, Accessory Dwelling Unit — accessed 2026-11-25
- SDCI Tip 116A, Establishing an Attached Accessory Dwelling Unit (updated November 19, 2026) — accessed 2026-11-25
- SDCI Tip 116B, Establishing a Detached Accessory Dwelling Unit (updated August 18, 2023) — accessed 2026-11-25
- City of Seattle, Building Permits (data.seattle.gov dataset 76t5-zqzr) — accessed 2026-11-22
- SDCI 2026 Fee Subtitle (SMC 22.900) — accessed 2026-11-05
Related Articles
Explore more content about similar topics and locations
How Much Does it Cost to Build an ADU in Seattle? (2026 Guide)
What a Seattle ADU really costs in 2026 — $77.7K–$219.1K attached vs. $199K–$303K+ detached. Full line-item breakdown, soft costs, build timeline, and rental ROI.
Seattle Flooring Cost 2026: Price Per Square Foot by Material
Seattle flooring costs $8.46–$20.19 per square foot installed in 2026 — LVP, engineered hardwood, tile, carpet. Real $/sqft, permit rules + a free calculator.
Seattle Fence Cost 2026: Price Per Linear Foot by Material
Seattle fence costs $18–$60 per linear foot in 2026 by material—chain link, cedar, vinyl, composite. Real $/ft, SDCI permit rules + a free calculator.
Browse more home renovation articles from Kolmo Construction