Bathroom remodel permits in City of Everett: fees, timeline & requirements (2026)

Everything you need to know about pulling a bathroom remodel permit in City of Everett, Washington — when one is required, what it costs, how long review takes, what documents are required, and which inspections you can expect. Cited to Everett Planning Department.

Permit required?
Yes — see threshold below
Permit fee
Fees set by jurisdiction. Plus separate electrical, plumbing, and mechanical permits.
Review timeline
10–21 days

When does a bathroom remodel need a permit in City of Everett?

Like-for-like fixture replacement in same location with no plumbing rerouting and no new circuits: typically exempt under 2021 IRC R105.2(2)(g). Any relocation, new fixture, new circuit, or shower-pan replacement triggers permits.

Required submittals

  • floor plan with fixture locations
  • plumbing diagram
  • electrical layout
  • waterproofing detail at tub/shower

Inspection sequence

  1. rough-in (electrical/plumbing/mechanical)
  2. shower-pan/waterproofing
  3. insulation if walls opened
  4. drywall
  5. final

Contractor specialties needed

general, electrical-01-or-02, plumbing

Notes & caveats

2021 IRC R105.1. GFCI/AFCI required at bathroom outlets per NEC 210.8 + WA amendments. Exhaust fan must vent to exterior (IRC R303). Tile shower waterproofing inspection required (PMG-001 / TCNA-aligned).

Bathroom remodel permit fee estimate in City of Everett

Worked example for a $22,000 bathroom remodel project (building permit). Your actual fee scales with project valuation.

Building permit fee$349.25
Plan review$227.01
WA state surcharge$4.5
Estimated total$580.76

Fees set by jurisdiction. Plus separate electrical, plumbing, and mechanical permits. Computed from the City of Everett fee bracket schedule · source ↗. Impact/utility fees may apply separately.

How to apply

  1. 1. Confirm your parcel's zoning & overlays. Run an address lookup for your City of Everett bathroom remodel — we'll pull your specific lot polygon, zoning, setbacks, and any shoreline/ECA/historic overlays.
  2. 2. Assemble submittals (4).
  3. 3. Submit through the city portal: Everett Planning Department
  4. 4. Track review (typical: 10–21 days). Respond to reviewer comments promptly.
  5. 5. Pay issuance fees (Fees set by jurisdiction. Plus separate electrical, plumbing, and mechanical permits.) and pick up the permit. Inspection card travels with the job.

Bathroom remodel permits in City of Everett — FAQ

When does a bathroom remodel need a permit in City of Everett?

Like-for-like fixture replacement in same location with no plumbing rerouting and no new circuits: typically exempt under 2021 IRC R105.2(2)(g). Any relocation, new fixture, new circuit, or shower-pan replacement triggers permits.

How much does a bathroom remodel permit cost in City of Everett?

For a $22,000 bathroom remodel project, the estimated City of Everett permit fee is about $580.76 — building fee $349.25 + plan review $227.01 + surcharges. Fees scale with project valuation per the city schedule.

How long does City of Everett take to review a bathroom remodel permit?

Typical review window: 10–21 days.

City of Everett resourcesPermit portal ↗Fee schedule ↗