Stormwater permits in City of Renton: fees, timeline & requirements (2026)

Everything you need to know about pulling a stormwater / drainage permit in City of Renton, Washington — when one is required, what it costs, how long review takes, what documents are required, and which inspections you can expect. Cited to Renton uses TRAKiT permits portal..

Permit required?
Yes — see threshold below
Permit fee
Drainage review fee commonly tiered by project size; small project ~$300-$800, full drainage review $1,500+. Apply via https://permits.rentonwa.gov.
Review timeline

When does a stormwater / drainage need a permit in City of Renton?

KC Surface Water Design Manual 2021 (KCC 9.04 + adopted by reference in most KC cities) sets the 2,000 sqft new+replaced impervious threshold for "small project" drainage review; ≥5,000 sqft triggers full drainage review. Different thresholds in critical-area drainage basins.

Required submittals

  • drainage report (full or simplified)
  • site plan with impervious calc
  • BMP / facility detail
  • geotech if infiltration claimed

Inspection sequence

  1. pre-construction (BMPs in place)
  2. facility installation
  3. final stabilization

Contractor specialties needed

general

Notes & caveats

Issuing body is city public works / county DPER, often parallel to the building permit. On-site infiltration / detention required where infeasible to discharge to municipal storm. Critical-area parcels (steep slope, salmon-bearing watercourse) get more conservative review.

Stormwater permit fee estimate in City of Renton

Worked example for a $25,000 stormwater / drainage project (building permit). Your actual fee scales with project valuation.

Building permit fee$391.25
Plan review$254.31
WA state surcharge$4.5
Estimated total$650.06

Drainage review fee commonly tiered by project size; small project ~$300-$800, full drainage review $1,500+. Apply via https://permits.rentonwa.gov. Computed from the City of Renton fee bracket schedule · source ↗. Impact/utility fees may apply separately.

How to apply

  1. 1. Confirm your parcel's zoning & overlays. Run an address lookup for your City of Renton stormwater / drainage — we'll pull your specific lot polygon, zoning, setbacks, and any shoreline/ECA/historic overlays.
  2. 2. Assemble submittals (4).
  3. 3. Submit through the city portal: Renton uses TRAKiT permits portal.
  4. 4. Track review (typical: ). Respond to reviewer comments promptly.
  5. 5. Pay issuance fees (Drainage review fee commonly tiered by project size; small project ~$300-$800, full drainage review $1,500+. Apply via https://permits.rentonwa.gov.) and pick up the permit. Inspection card travels with the job.

Stormwater permits in City of Renton — FAQ

When does a stormwater / drainage need a permit in City of Renton?

KC Surface Water Design Manual 2021 (KCC 9.04 + adopted by reference in most KC cities) sets the 2,000 sqft new+replaced impervious threshold for "small project" drainage review; ≥5,000 sqft triggers full drainage review. Different thresholds in critical-area drainage basins.

How much does a stormwater / drainage permit cost in City of Renton?

For a $25,000 stormwater / drainage project, the estimated City of Renton permit fee is about $650.06 — building fee $391.25 + plan review $254.31 + surcharges. Fees scale with project valuation per the city schedule.

City of Renton resourcesPermit portal ↗Fee schedule ↗