HVAC permits in Tacoma: fees, timeline & requirements (2026)

Everything you need to know about pulling an HVAC / mechanical permit in Tacoma, Washington — when one is required, what it costs, how long review takes, what documents are required, and which inspections you can expect. Cited to Tacoma Planning & Development Services.

Look up your Tacoma address

Free lookup, no account needed — the office that issues the permit at your address, cited to Tacoma's source.

Permit required?
Permit if: a fixed system.
Permit fee
Tacoma prices replacing an individual mechanical unit, duct work or an exhaust fan, or gas piping in a house or duplex at 2.81% of its construction value, $190 at the least (PDS Fee Schedule Table 9-3); a mechanical e-permit is $140 with no plan review fee.
Review timeline
Not published by the city

When does HVAC work need a permit in Tacoma?

Exempt: portable heating/ventilation/cooling appliances; portable evaporative coolers; steam/hot/chilled-water piping within heating/cooling equipment regulated by code; minor part replacements that don't alter equipment approval; self-contained refrigeration systems with ≤10 lb refrigerant or ≤1 hp motors; portable-fuel-cell appliances not connected to fixed piping or power grid.

How Tacoma adopted this rule

The threshold comes from the state code (WAC 51.52), which Tacoma adopts by reference in the provision quoted below.

“The IMC as adopted by the State Building Code as defined in TMC § 2.02.100 is hereby included in the City of Tacoma Mechanical Code as adopted by this chapter. Fees shall be in accordance with TMC Chapter 2.09. (Repealed and reenacted by Ord. 27890 Ex. A, 2010-06-15; repealed and reenacted by Ord. 28155 Ex. A, 2013-06-11; Ord. 28363 Ex. A, 2016-06-14; Ord. 28957 Ex. A, 2024-03-05 )”
Source ↗verified 2026-04-29

What Tacoma says in its own permit handout

From Mechanical Equipment Locations, published by Tacoma. This is the jurisdiction's own guidance on its permit process, not the ordinance text — where the two differ, the code governs.

“Mechanical equipment may not be located within a required side yard setback (7.5 feet or 5 feet, depending on zone) or open yard space. In all cases, chain link fencing, with or without slats is prohibited to use for screening.”
Handout ↗read 2026-09-05

Required submittals

  • Equipment specs (model #, capacity)
  • Manual J/S/D for new system
  • Gas piping diagram if applicable
  • Electrical permit cross-reference

Inspection sequence

  1. Rough-in / gas pressure test
  2. Final

Contractor specialties needed

General contractor

Who can do this work in Tacoma?

Kolmo Construction is a licensed Washington general contractor — KOLMOL*753JS, active through April 10, 2027, bonded and insured — working throughout Tacoma and Pierce County. Kolmo manages the HVAC / mechanical job from start to finish: a licensed HVAC subcontractor performs the work and pulls the permit, and Kolmo coordinates the scope, schedule, inspections and any related construction. Call (206) 410-5100 for a Tacoma HVAC / mechanical quote.

Notes & caveats

Tacoma's exemptions for heating, cooling and ventilation are IRC R105.2's mechanical items, which TMC 2.02.010 adopts unamended (TMC 2.02.540 changes only the building and electrical parts): portable heating, ventilation and cooling appliances, portable evaporative coolers, steam, hot- or chilled-water piping within the equipment, small self-contained refrigeration systems (10 lb of refrigerant or less, or a motor of 1 hp or less), and "Replacement of any minor part that does not alter approval of equipment or make such equipment unsafe." Installing or replacing a furnace, heat pump, air conditioner or duct work needs a mechanical permit (IRC R105.1).

How to apply yourself

  1. 1. Check who issues the permit. Run an address lookup for your HVAC work in Tacoma — we'll confirm which office issues the permit at that address.
  2. 2. Assemble submittals: the 4 documents under Required submittals above.
  3. 3. Submit through the city portal: Tacoma Planning & Development Services ↗
  4. 4. Track review. Respond to reviewer comments promptly.
  5. 5. Pay issuance fees (Tacoma's fee schedule sets them) and pick up the permit. Inspection card travels with the job.

Or have Kolmo do it

Kolmo runs the job: a licensed HVAC subcontractor does the HVAC / mechanical work and pulls the permit, and Kolmo coordinates the scope, schedule, inspections and any related construction.

(206) 410-5100

Licensed WA general contractor KOLMOL*753JS · bonded & insured

HVAC permits in Tacoma — FAQ

When does HVAC work need a permit in Tacoma?

Exempt: portable heating/ventilation/cooling appliances; portable evaporative coolers; steam/hot/chilled-water piping within heating/cooling equipment regulated by code; minor part replacements that don't alter equipment approval; self-contained refrigeration systems with ≤10 lb refrigerant or ≤1 hp motors; portable-fuel-cell appliances not connected to fixed piping or power grid.

How much does an HVAC / mechanical permit cost in Tacoma?

Tacoma prices replacing an individual mechanical unit, duct work or an exhaust fan, or gas piping in a house or duplex at 2.81% of its construction value, $190 at the least (PDS Fee Schedule Table 9-3); a mechanical e-permit is $140 with no plan review fee. The technology (5%), emergency preparedness (5%) and reserve fund (2%) surcharges are added. A new or altered circuit is Tacoma Power's electrical permit, $89 for 1 to 4 circuits where the service is not changed (TMC 12.06A.250).