Attached ADU (AADU) Permits in Renton

An ADU built inside or attached to the primary residence — basement conversion, garage conversion, or bump-out addition. Lower cost; constrained by the primary footprint.

Free lookup: your lot’s zoning and setbacks, with an attached ADU placed on it to move and turn.

Permit fees in Renton

Set by the Renton fee schedule.

Renton fee schedule

Renton prices an ADU's building permit on the value of the work: $1,062.23 for the first $50,000 plus $11.53 for each $1,000 more up to $100,000, and $1,638.89 for the first $100,000 plus $9.17 for each $1,000 more up to $500,000. Plan check is 65% of the permit fee, and $0 for an ADU built from the City's Permit Ready ADU (PRADU) plans, which are already reviewed; the $6.50 state building code fee applies. The storm water system development charge for an ADU is $2,350. The City adds its 5% technology surcharge to its building fees (Fee Schedule 2025-2026). Apply via permitting.rentonwa.gov.

Review timeline

Not published by Renton.

What Renton asks for with an attached ADU

Every application (8)

  • Building permit application (permitting.rentonwa.gov)
  • Site address
  • Legal description (from KC Assessor)
  • King County Assessor parcel number (PIN)
  • Site Plan
  • ADU size + lot-coverage compliance (RMC 4-2-110C)
  • Floor plan
  • Renton submittal routing & prerequisites (RMC 4-8-120, Table 4-8-120B)

Where the lot or the work calls for it

Where the ADU adds onto the house or changes its outside walls, windows or roof

  • Typical building / wall section
  • Building elevations N/S/E/W
  • Major materials schedule

Where the work changes the outside walls, windows or roof

  • Glazing + door schedule (NFRC U-factor / SHGC)
  • WSEC energy compliance, prescriptive path
  • Energy Code Checklist, Residential (WSU Energy Program form)

From the city’s own documents: Renton Municipal Code 4-8-120 — Submittal Requirements, Specific to Application Type (Table 4-8-120B; 4-8-120D definitions) · Renton Municipal Code 4-2-110C — Development Standards for Accessory Dwelling Units, last read October 17, 2026. An address’s own page checks its lot for slopes, flood zones and critical areas.

AADU-specific requirements

  • Egress on every bedroom — IRC R310 net clear opening ≥5.7 sf; sill ≤44″ from floor.
  • Smoke + CO alarms — interconnected throughout primary + AADU per IRC R314/R315.
  • 1-hr separation — required between AADU and primary in some cases; otherwise a continuous draft stop.
  • Independent kitchen + bath — full plumbing + cooking provision in the AADU.
  • Address or unit number — the city or county assigns addresses; ask the permit center whether the unit gets its own.