Detached ADU (DADU) Permits in Bellevue

A standalone backyard cottage with its own foundation, roof, and exterior. Maximum flexibility on layout; highest construction cost. State law bars a city maximum below 1,000 sq ft of gross floor area, except on lots with critical areas (RCW 36.70A.681).

Free lookup: your lot’s zoning and setbacks, with a detached ADU placed on it to move and turn.

Permit fees in Bellevue

Set by the Bellevue fee schedule.

Bellevue fee schedule

Bellevue prices an ADU's building permit on the value of the work: $728.65 for the first $25,000 plus $19.06 for each $1,000 more up to $50,000, $1,205.15 for the first $50,000 plus $12.33 for each $1,000 more up to $100,000, and $1,821.65 for the first $100,000 plus $10.77 for each $1,000 more up to $1,000,000, each prorated. Plan review is 65% of that fee and the operations fee $53 (Ordinance 6879), and the state building code fee is $6.50 on a residential permit (RCW 19.27.085). Land use, utility, transportation and clearing and grading reviews add their own fees by permit type (Ordinance 6879, Tables 13, 20, 22 and 25). The school impact fee on an ADU is half the principal unit's, and the Issaquah and Renton school districts' fees under the ordinance are $0. Bellevue issues its own electrical permits, priced on the value of the electrical work, $79 up to $500. Apply via mybuildingpermit.com.

Review timeline

Typical: 21–90 business days

What Bellevue asks for with a detached ADU

Every application (20)

  • MyBuildingPermit application
  • Document Waiver Form, one for each required document that does not apply
  • Arborist Report
  • Residential Site Plan
  • Addressing Site Plan
  • Boundary and Topographic Survey
  • CSWPPP Short Form, with its erosion and sediment control plan
  • Storm Drainage Report
The other 12
  • Civil plans for residential projects (site and erosion control, drainage, grading)
  • Foundation plan
  • Floor plan
  • Roof plan
  • Roof + floor framing plan
  • Typical building / wall section
  • Building elevations N/S/E/W
  • Glazing + door schedule (NFRC U-factor / SHGC)
  • Structural design notes (loads, materials, inspections)
  • Major materials schedule
  • WSEC energy compliance, prescriptive path
  • Energy code compliance forms (WSU), such as the Code Compliance Calculator

Where the lot or the work calls for it

Where a building is taken down

  • Disconnection of Water/Sewer Service Form

Where the lot has a steep slope, is in a landslide hazard area or has ground that needs a soils study

  • Structural or lateral calculations

From the city’s own documents: City of Bellevue — New House Construction or Large Addition (BS permit) · City of Bellevue Plan Submittal Resources — Arborist Report · City of Bellevue Plan Submittal Resources — Residential Site Plan and 8 more, last read October 21, 2026. An address’s own page checks its lot for slopes, flood zones and critical areas.

The other 8 documents