Right-of-way permits in City of Bellevue: fees, timeline & requirements (2026)

Everything you need to know about pulling a right-of-way permit in City of Bellevue, Washington — when one is required, what it costs, how long review takes, what documents are required, and which inspections you can expect. Cited to Bellevue Development Services.

Permit required?
Yes — see threshold below
Permit fee
Fees vary by scope — see Bellevue Permit Fees and Payment, or the Permit Fee Estimator at permitfeeestimator.bellevuewa.gov.
Review timeline

When does a right-of-way need a permit in City of Bellevue?

A Residential Right of Way permit covers work in the right of way associated with existing single-family home construction or major remodels. Commercial projects, multifamily development, and plat infrastructure use the Commercial Right of Way permit instead — that one is required for hauling, parking, and staging whether or not there is construction in the right of way. Street Use permits cover non-disturbing uses (sidewalk cafes, parades, block parties, closures).

From City of Bellevue's own page

This permit may be issued for work in the right of way associated with existing single family home construction or major remodels: installation of driveways, driveway reconstruction or relocation, landscaping, fences/walls, city water/sewer/storm connections and other uses.
Source ↗verified 2026-08-11

Required submittals

  • Bill To Form
  • Site plan showing site location, address, and adjacent street names
  • North arrow and scale (1 inch = 20 feet to 1 inch = 50 feet)
  • Driveway entrances
  • Proposed scope of work in the right of way
  • Plan/profile for roadway restoration after trenching

Inspection sequence

  1. pre-construction
  2. subgrade / base
  3. final ROW restoration

Contractor specialties needed

general

Notes & caveats

Apply online through MyBuildingPermit.com. Right of Way Management: [email protected], 425-452-4189.

Right-of-way permit fee estimate in City of Bellevue

Worked example for a $25,000 right-of-way project (building permit). Your actual fee scales with project valuation.

Building permit fee$391.25
Plan review$254.31
WA state surcharge$4.5
Estimated total$650.06

Fees vary by scope — see Bellevue Permit Fees and Payment, or the Permit Fee Estimator at permitfeeestimator.bellevuewa.gov. Computed from the City of Bellevue fee bracket schedule · source ↗. Impact/utility fees may apply separately.

How to apply

  1. 1. Confirm your parcel's zoning & overlays. Run an address lookup for your City of Bellevue right-of-way — we'll pull your specific lot polygon, zoning, setbacks, and any shoreline/ECA/historic overlays.
  2. 2. Assemble submittals (6).
  3. 3. Submit through the city portal: Bellevue Development Services
  4. 4. Track review (typical: ). Respond to reviewer comments promptly.
  5. 5. Pay issuance fees (Fees vary by scope — see Bellevue Permit Fees and Payment, or the Permit Fee Estimator at permitfeeestimator.bellevuewa.gov.) and pick up the permit. Inspection card travels with the job.

Right-of-way permits in City of Bellevue — FAQ

When does a right-of-way need a permit in City of Bellevue?

A Residential Right of Way permit covers work in the right of way associated with existing single-family home construction or major remodels. Commercial projects, multifamily development, and plat infrastructure use the Commercial Right of Way permit instead — that one is required for hauling, parking, and staging whether or not there is construction in the right of way. Street Use permits cover non-disturbing uses (sidewalk cafes, parades, block parties, closures).

How much does a right-of-way permit cost in City of Bellevue?

For a $25,000 right-of-way project, the estimated City of Bellevue permit fee is about $650.06 — building fee $391.25 + plan review $254.31 + surcharges. Fees scale with project valuation per the city schedule.

City of Bellevue resourcesPermit portal ↗Fee schedule ↗