Right-of-way permits in Kent: fees, timeline & requirements (2026)
Everything you need to know about pulling a right-of-way permit in Kent, Washington — when one is required, what it costs, how long review takes, what documents are required, and which inspections you can expect. Cited to Kent Economic and Community Development.
Free lookup, no account needed — your lot lines, where the lot meets the street, cited to Kent's source.
When does right-of-way work need a permit in Kent?
Issued by city public works (or SDOT in Seattle) under local ROW ordinance. Triggered by physical occupation of or work within the public ROW including driveway aprons, curb cuts, sidewalk replacement, utility tie-ins, hauling routes, and temporary construction staging.
From Kent's own code
“6.07.030 Permit required. It shall be unlawful for anyone to use any public place for private purposes without having first obtained a street use permit from the director as required in this chapter and without complying with all the provisions of this chapter. (Ord. No. 3471, § 1, 8-17-99; Ord. No. 3534, § 1, 12-5-00)”Source ↗verified 2026-09-06
Required submittals
- ROW work plan / sketch
- Traffic-control plan if arterial
- Certificate of insurance
- Bond if required
Inspection sequence
- Pre-construction
- Subgrade / base
- Final ROW restoration
Contractor specialties needed
General contractor
Who can do this work in Kent?
Kolmo Construction is a licensed Washington general contractor — KOLMOL*753JS, active through April 10, 2027, bonded and insured — working throughout Kent and King County. Kolmo prepares the drawings and submittals, files the right-of-way permit with Kent Economic and Community Development, carries the project through review and inspections, and performs the construction. Call (206) 410-5100 for a Kent right-of-way quote.
Notes & caveats
Issuing body is city public works, not the building department. Often required as a precondition to a building permit (e.g. addition w/ new driveway). Bond + insurance commonly required. Traffic-control plan for arterial work.
How to apply yourself
- 1. Find where your lot meets the street. Run an address lookup for your right-of-way work in Kent — we'll pull your lot lines as the county maps them, which show where the lot ends and the public right-of-way begins.
- 2. Assemble submittals: the 4 documents under Required submittals above.
- 3. Submit through the city portal: Kent Economic and Community Development ↗
- 4. Track review. Respond to reviewer comments promptly.
- 5. Pay issuance fees (Kent's fee schedule sets them) and pick up the permit. Inspection card travels with the job.
Or have Kolmo do it
Kolmo prepares the drawings and submittals, files with Kent Economic and Community Development, handles reviewer comments, and builds the project.
Licensed WA general contractor KOLMOL*753JS · bonded & insured
Right-of-way permits in Kent — FAQ
When does right-of-way work need a permit in Kent?
Issued by city public works (or SDOT in Seattle) under local ROW ordinance. Triggered by physical occupation of or work within the public ROW including driveway aprons, curb cuts, sidewalk replacement, utility tie-ins, hauling routes, and temporary construction staging.
How much does a right-of-way permit cost in Kent?
Kent posts no right-of-way permit fee: for Public Works fees, the City's permit page says to call Development Engineering at 253-856-5490. Apply through the City of Kent Permit Portal (https://sso.kentwa.gov/).