Demolition permits in City of Kirkland: fees, timeline & requirements (2026)
Everything you need to know about pulling a demolition permit in City of Kirkland, Washington — when one is required, what it costs, how long review takes, what documents are required, and which inspections you can expect. Cited to Apply via MyBuildingPermit.com..
When does a demolition need a permit in City of Kirkland?
2021 IBC Section 105.1 + WA-adopted IRC R105.1: demolition of any structure or portion thereof requires a permit. Tear-out of interior finishes only is generally treated as alteration. Asbestos / lead notification often required separately under WAC 173-303 / 296-62.
Required submittals
- site plan
- utility disconnect confirmations
- asbestos survey (pre-1981 structures)
- erosion / sediment control plan
- haul route if structure >1500 sqft
Inspection sequence
- pre-demo (utilities + erosion)
- mid-demo if multi-day
- final site stabilization
Contractor specialties needed
general
Notes & caveats
Disconnect notices required from utilities (gas, electric, water, sewer) before issuance. Erosion control plan required where soil is disturbed. Bonded contractor typically required. Site stabilization + capped sewer line at completion.
Demolition permit fee estimate in City of Kirkland
Worked example for a $25,000 demolition project (building permit). Your actual fee scales with project valuation.
| Building permit fee | $391.25 |
| Plan review | $254.31 |
| WA state surcharge | $4.5 |
| Estimated total | $650.06 |
Demolition fees commonly charged as flat fee or by structure size. State surcharge $4.50 applies. Apply via https://mybuildingpermit.com. Computed from the City of Kirkland fee bracket schedule · source ↗. Impact/utility fees may apply separately.
How to apply
- 1. Confirm your parcel's zoning & overlays. Run an address lookup for your City of Kirkland demolition — we'll pull your specific lot polygon, zoning, setbacks, and any shoreline/ECA/historic overlays.
- 2. Assemble submittals (5).
- 3. Submit through the city portal: Apply via MyBuildingPermit.com. ↗
- 4. Track review (typical: —). Respond to reviewer comments promptly.
- 5. Pay issuance fees (Demolition fees commonly charged as flat fee or by structure size. State surcharge $4.50 applies. Apply via https://mybuildingpermit.com.) and pick up the permit. Inspection card travels with the job.
Demolition permits in City of Kirkland — FAQ
When does a demolition need a permit in City of Kirkland?
2021 IBC Section 105.1 + WA-adopted IRC R105.1: demolition of any structure or portion thereof requires a permit. Tear-out of interior finishes only is generally treated as alteration. Asbestos / lead notification often required separately under WAC 173-303 / 296-62.
How much does a demolition permit cost in City of Kirkland?
For a $25,000 demolition project, the estimated City of Kirkland permit fee is about $650.06 — building fee $391.25 + plan review $254.31 + surcharges. Fees scale with project valuation per the city schedule.