Side-by-side: which of Seattle, Bellevue, Kirkland, Redmond, Sammamish, Issaquah, Renton, Kent, Federal Way, Mercer Island, Shoreline, Tacoma, Lakewood, Puyallup, Everett, Lynnwood require a permit for a demolition, and what triggers one — each row quoted from the city's own code or permit page, with the source linked. Fees and review times appear where the city publishes them.
16 of 16 cities have authoritative rules on file · 16 always require a permit · 0 depend on the scope · 0 do not.
King County
| Jurisdiction | Permit? | Threshold | Fee | Review days | Source |
|---|---|---|---|---|---|
City of Bellevue city | Always | Demolishing a structure or a substantial part of one needs a permit; asbestos and lead notifications are separate. 2021 IBC Section 105.1 + WA-adopted IRC R105.1: demolition of any structure or portion thereof requires a permit. Tear-out of interior finishes only is generally treated as alteration. Asbestos / lead notification often required separately under WAC 173-303 / 296-62. | Demolition fees commonly charged as flat fee or by structure size. State surcharge $6.50 applies. Apply via https://mybuildingpermit.com. | — | Cite verified 2026-04-26 |
City of Federal Way city | Always | Demolishing a structure or a substantial part of one needs a permit; asbestos and lead notifications are separate. 2021 IBC Section 105.1 + WA-adopted IRC R105.1: demolition of any structure or portion thereof requires a permit. Tear-out of interior finishes only is generally treated as alteration. Asbestos / lead notification often required separately under WAC 173-303 / 296-62. | Demolition fees commonly charged as flat fee or by structure size. State surcharge $6.50 applies. | — | Cite verified 2026-09-24 |
City of Issaquah city | Always | Demolishing a structure or a substantial part of one needs a permit; asbestos and lead notifications are separate. 2021 IBC Section 105.1 + WA-adopted IRC R105.1: demolition of any structure or portion thereof requires a permit. Tear-out of interior finishes only is generally treated as alteration. Asbestos / lead notification often required separately under WAC 173-303 / 296-62. | Demolition fees commonly charged as flat fee or by structure size. State surcharge $6.50 applies. Apply via https://mybuildingpermit.com. | — | Cite verified 2026-05-16 |
City of Kent city | Always | Demolishing a structure or a substantial part of one needs a permit; asbestos and lead notifications are separate. 2021 IBC Section 105.1 + WA-adopted IRC R105.1: demolition of any structure or portion thereof requires a permit. Tear-out of interior finishes only is generally treated as alteration. Asbestos / lead notification often required separately under WAC 173-303 / 296-62. | Demolition fees commonly charged as flat fee or by structure size. State surcharge $6.50 applies. Apply via https://mybuildingpermit.com. | — | Cite verified 2026-09-24 |
City of Kirkland city | Always | Demolishing a structure or a substantial part of one needs a permit; asbestos and lead notifications are separate. 2021 IBC Section 105.1 + WA-adopted IRC R105.1: demolition of any structure or portion thereof requires a permit. Tear-out of interior finishes only is generally treated as alteration. Asbestos / lead notification often required separately under WAC 173-303 / 296-62. | Demolition fees commonly charged as flat fee or by structure size. State surcharge $6.50 applies. Apply via https://mybuildingpermit.com. | — | Cite verified 2026-05-29 |
City of Mercer Island city | Always | Demolishing a structure or a substantial part of one needs a permit; asbestos and lead notifications are separate. 2021 IBC Section 105.1 + WA-adopted IRC R105.1: demolition of any structure or portion thereof requires a permit. Tear-out of interior finishes only is generally treated as alteration. Asbestos / lead notification often required separately under WAC 173-303 / 296-62. | Demolition fees commonly charged as flat fee or by structure size. State surcharge $6.50 applies. | — | Cite verified 2026-05-02 |
City of Redmond city | Always | Demolishing a structure or a substantial part of one needs a permit; asbestos and lead notifications are separate. 2021 IBC Section 105.1 + WA-adopted IRC R105.1: demolition of any structure or portion thereof requires a permit. Tear-out of interior finishes only is generally treated as alteration. Asbestos / lead notification often required separately under WAC 173-303 / 296-62. | Demolition fees commonly charged as flat fee or by structure size. State surcharge $6.50 applies. Apply via https://eplans.redmond.gov. | — | Cite verified 2026-05-29 |
City of Renton city | Always | Demolishing a structure or a substantial part of one needs a permit; asbestos and lead notifications are separate. 2021 IBC Section 105.1 + WA-adopted IRC R105.1: demolition of any structure or portion thereof requires a permit. Tear-out of interior finishes only is generally treated as alteration. Asbestos / lead notification often required separately under WAC 173-303 / 296-62. | Demolition fees commonly charged as flat fee or by structure size. State surcharge $6.50 applies. Apply via https://permits.rentonwa.gov. | — | Cite verified 2026-09-24 |
City of Sammamish city | Always | Demolishing a structure or a substantial part of one needs a permit; asbestos and lead notifications are separate. 2021 IBC Section 105.1 + WA-adopted IRC R105.1: demolition of any structure or portion thereof requires a permit. Tear-out of interior finishes only is generally treated as alteration. Asbestos / lead notification often required separately under WAC 173-303 / 296-62. | Demolition fees commonly charged as flat fee or by structure size. State surcharge $6.50 applies. Apply via https://mybuildingpermit.com. | — | Cite verified 2026-05-29 |
City of Seattle city | Always | Demolishing a structure or a substantial part of one needs a permit; asbestos and lead notifications are separate. 2021 IBC Section 105.1 + WA-adopted IRC R105.1: demolition of any structure or portion thereof requires a permit. Tear-out of interior finishes only is generally treated as alteration. Asbestos / lead notification often required separately under WAC 173-303 / 296-62. | Demolition fees commonly charged as flat fee or by structure size. State surcharge $6.50 applies. | — | Cite verified 2026-05-02 |
City of Shoreline city | Always | Demolishing a structure or a substantial part of one needs a permit; asbestos and lead notifications are separate. 2021 IBC Section 105.1 + WA-adopted IRC R105.1: demolition of any structure or portion thereof requires a permit. Tear-out of interior finishes only is generally treated as alteration. Asbestos / lead notification often required separately under WAC 173-303 / 296-62. | Demolition fees commonly charged as flat fee or by structure size. State surcharge $6.50 applies. Apply electronically via eTRAKiT (https://www.shorelinewa.gov/government/departments/planning-community-development/permit-center-remote-services/register-for-a-professional-etrakit-account). | — | Cite verified 2026-05-17 |
Pierce County
| Jurisdiction | Permit? | Threshold | Fee | Review days | Source |
|---|---|---|---|---|---|
City of Lakewood city | Always | Demolishing a structure or a substantial part of one needs a permit; asbestos and lead notifications are separate. 2021 IBC Section 105.1 + WA-adopted IRC R105.1: demolition of any structure or portion thereof requires a permit. Tear-out of interior finishes only is generally treated as alteration. Asbestos / lead notification often required separately under WAC 173-303 / 296-62. | Demolition fees commonly charged as flat fee or by structure size. State surcharge $6.50 applies. | — | Cite verified 2026-05-02 |
City of Puyallup city | Always | Demolishing a structure or a substantial part of one needs a permit; asbestos and lead notifications are separate. 2021 IBC Section 105.1 + WA-adopted IRC R105.1: demolition of any structure or portion thereof requires a permit. Tear-out of interior finishes only is generally treated as alteration. Asbestos / lead notification often required separately under WAC 173-303 / 296-62. | Demolition fees commonly charged as flat fee or by structure size. State surcharge $6.50 applies. | — | Cite verified 2026-05-02 |
City of Tacoma city | Always | Demolishing a structure or a substantial part of one needs a permit; asbestos and lead notifications are separate. 2021 IBC Section 105.1 + WA-adopted IRC R105.1: demolition of any structure or portion thereof requires a permit. Tear-out of interior finishes only is generally treated as alteration. Asbestos / lead notification often required separately under WAC 173-303 / 296-62. | Demolition fees commonly charged as flat fee or by structure size. State surcharge $6.50 applies. | — | Cite verified 2026-05-02 |
Snohomish County
| Jurisdiction | Permit? | Threshold | Fee | Review days | Source |
|---|---|---|---|---|---|
City of Everett city | Always | Demolishing a structure or a substantial part of one needs a permit; asbestos and lead notifications are separate. 2021 IBC Section 105.1 + WA-adopted IRC R105.1: demolition of any structure or portion thereof requires a permit. Tear-out of interior finishes only is generally treated as alteration. Asbestos / lead notification often required separately under WAC 173-303 / 296-62. | Demolition fees commonly charged as flat fee or by structure size. State surcharge $6.50 applies. | — | Cite verified 2026-04-26 |
City of Lynnwood city | Always | Demolishing a structure or a substantial part of one needs a permit; asbestos and lead notifications are separate. 2021 IBC Section 105.1 + WA-adopted IRC R105.1: demolition of any structure or portion thereof requires a permit. Tear-out of interior finishes only is generally treated as alteration. Asbestos / lead notification often required separately under WAC 173-303 / 296-62. | Demolition fees commonly charged as flat fee or by structure size. State surcharge $6.50 applies. | — | Cite verified 2026-05-02 |
How this table is built
Each row reflects the most-recently-verified authoritative rule on file for that jurisdiction and project type. “Pending verification” means we have the jurisdiction in our database but haven't yet personally checked the city page for demolition rules — those rows fall back to county or WA-state baselines until verified. Sources link directly to the city or county page we read on the verified-on date. See our data-quality leaderboard for how we keep these current.