Kitchen remodel permits in Lynnwood: fees, timeline & requirements (2026)

Everything you need to know about pulling a kitchen remodel permit in Lynnwood, Washington — when one is required, what it costs, how long review takes, what documents are required, and which inspections you can expect. Cited to Lynnwood Development & Business Services.

Look up your Lynnwood address

Free lookup, no account needed — the office that issues the permit at your address, and a layout of the room, cited to Lynnwood's source.

Permit required?
Permit if: plumbing moved or added · a sink or other fixture replaced, even in the same spot · a faucet replaced · a defective trap, drain, waste or vent pipe replaced · new or moved electrical circuits · gas, venting or mechanical work · a wall moved or removed, or structural work.
Permit fee
About $1,569 for a $35,000 project, when a permit is needed
Review timeline
Not published by the city

When does a kitchen remodel need a permit in Lynnwood?

Cosmetic-only refresh (cabinets, countertops, flooring, paint) without structural/electrical/plumbing changes is generally exempt under 2021 IRC R105.2 (work exempt from permit). Any new circuit, fixture relocation, or structural change requires permits.

How Lynnwood adopted this rule

The threshold comes from the state code (WAC 51.51), which Lynnwood adopts by reference in the provision quoted below.

“As amended by this chapter and the State of Washington Building Code Council under Chapter 51-51 WAC, the latest adopted version of the International Residential Code (IRC), published by the International Code Council, except Chapters 11 and 25 through 43”
Source ↗verified 2026-10-02

Required submittals

  • Floor plan with fixture locations
  • Electrical layout
  • Plumbing diagram
  • WSEC compliance form if envelope/lighting affected

Inspection sequence

  1. Rough-in (electrical/plumbing/mechanical)
  2. Insulation if walls opened
  3. Drywall
  4. Final

Contractor specialties needed

General contractor · Electrician (journey-level 01 or residential 02) · Plumber

Who can do this work in Lynnwood?

Kolmo Construction is a licensed Washington general contractor — KOLMOL*753JS, active through April 10, 2027, bonded and insured — working throughout Lynnwood and Snohomish County. Kolmo prepares the drawings and submittals, files the kitchen remodel permit with Lynnwood Development & Business Services, carries the project through review and inspections, and performs the construction. Call (206) 410-5100 for a Lynnwood kitchen remodel quote.

Notes & caveats

2021 IRC R105.1 requires building permits for "construction, enlargement, alteration, repair, movement, removal, conversion, or demolition" except work listed in R105.2. New electrical circuits → electrical permit (WAC 296-46B). New/relocated plumbing fixtures → plumbing permit (UPC, WAC 51-56). New gas line or range hood vent → mechanical permit.

Kitchen remodel permit fee estimate in Lynnwood

Worked example for a $35,000 kitchen remodel project (building permit). Your actual fee scales with project valuation.

Building permit fee$923.83
Plan review$600.49
Technology surcharge$38.11
WA state surcharge$6.50
Estimated total$1,568.93

Lynnwood prices a kitchen remodel's building permit on the value of the work, by the ICC valuation table or the building's square footage, whichever is greater: $114 up to $1,000, $114 for the first $1,000 plus $5.74 for each $100 more up to $2,000, $171.35 for the first $2,000 plus $25.23 for each $1,000 more up to $25,000, and $751.73 for the first $25,000 plus $17.21 for each $1,000 more up to $50,000. Plan review is 65% of that fee. Plumbing and mechanical permits for a remodel are each $257 for up to 4 fixtures or pieces of equipment and $22 for each one more, and the City, not L&I, issues the electrical permit: $147 for up to 10 circuits added or altered, $15 for each more circuit up to a $200 total. A 2.5% technology fee is added (LMC 3.104). Computed from Lynnwood's adopted fee schedule · source ↗. Land use, fire and engineering review, intake, impact and utility fees, where they apply, are charged separately.

How to apply yourself

  1. 1. Check who issues the permit. Run an address lookup for your kitchen remodel in Lynnwood — we'll confirm which office issues the permit at that address, and you can lay out the room.
  2. 2. Assemble submittals: the 4 documents under Required submittals above.
  3. 3. Submit through the city portal: Lynnwood Development & Business Services ↗
  4. 4. Track review. Respond to reviewer comments promptly.
  5. 5. Pay issuance fees (about $1,569 for a $35,000 project) and pick up the permit. Inspection card travels with the job.

Or have Kolmo do it

Kolmo prepares the drawings and submittals, files with Lynnwood Development & Business Services, handles reviewer comments, and builds the project.

(206) 410-5100

Licensed WA general contractor KOLMOL*753JS · bonded & insured

Kitchen remodel permits in Lynnwood — FAQ

When does a kitchen remodel need a permit in Lynnwood?

Cosmetic-only refresh (cabinets, countertops, flooring, paint) without structural/electrical/plumbing changes is generally exempt under 2021 IRC R105.2 (work exempt from permit). Any new circuit, fixture relocation, or structural change requires permits.

How much does a kitchen remodel permit cost in Lynnwood?

For a $35,000 kitchen remodel project, the estimated Lynnwood permit fee is about $1,568.93 (building fee $923.83 + plan review $600.49 + surcharges) from Lynnwood's adopted fee schedule. Land use, fire and engineering review, intake, impact and utility fees, where they apply, are charged separately.