Detached ADU (DADU) Permits in Everett
A standalone backyard cottage with its own foundation, roof, and exterior. Maximum flexibility on layout; highest construction cost. State law bars a city maximum below 1,000 sq ft of gross floor area, except on lots with critical areas (RCW 36.70A.681).
Free lookup: your lot’s zoning and setbacks, with a detached ADU placed on it to move and turn.
Permit fees in Everett
Set by the Everett fee schedule.
Everett fee scheduleEverett sets an ADU's valuation at $193 a square foot and prices the building permit on it: $818.75 plus $21.75 for each $1,000 over $25,000 up to $50,000, $1,362.50 plus $20.75 for each $1,000 over $50,000 up to $100,000, and $2,400 plus $8.75 for each $1,000 over $100,000 up to $500,000. Plan review adds 75% of that fee and Planning's review 10%, plus the $6.50 state building code fee. For a new dwelling unit the mechanical permit is the $130 base fee plus $60 for up to 1,000 square feet of conditioned floor space or $90 up to 2,000; plumbing is $130 plus $20 for each fixture; and the City's electrical permit is $100 under 1,000 square feet or $150 up to 2,000. The transportation impact fee for an ADU is $3,115, but a net increase of one ADU triggers none; ADUs pay no school impact fee; the parks impact fee ($1,133 for a studio or one bedroom, $2,268 for two, $3,401 for three or more) is halved for one or two ADUs added to a lot whose house stays. Where the ADU takes a new 3/4-inch City water meter, water and sewer system development fees are $9,433 ($5,159 water, $4,274 sewer), and new impervious area pays $0.3624 a square foot in stormwater system development fees.
Review timeline
Typical: 30–90 business days
Measured, detached ADU: half issued within 312 days of application, 80% within 45475 permits, last 12 months. Source: City of Everett building permits, data.everettwa.gov dataset 3w3u-656c (residential types).
What Everett asks for with a detached ADU
Every application (17)
- Residential Building permit application (Accessory dwelling unit (ADU or DADU)), online permitting portal
- Submittal Checklist Worksheet, completed and signed
- Site address
- Legal description (from Snohomish County Assessor)
- Snohomish County tax parcel ID
- Site plan
- Site Work permit, applied for at the same time
- Foundation plan
The other 9
- Floor plan
- Roof + floor framing plan
- Typical building / wall section
- Building elevations N/S/E/W
- Glazing + door schedule (NFRC U-factor / SHGC)
- Structural design notes (loads, materials, inspections)
- Major materials schedule
- WSEC energy compliance, prescriptive path
- Energy Code Compliance Worksheets: the City's Residential Energy Code compliance checklist and WSU's 2021 forms
Where the lot or the work calls for it
Where the lot has a wetland, has a stream or has fish and wildlife habitat
- Critical Area/Mitigation Report (EMC 19.37)
Where the lot has a steep slope or is in a landslide hazard area
- Geotechnical report
From the city’s own documents: City of Everett — Residential Building Permit Submittal Checklist, Subtype: Accessory Dwelling Unit (ADU or DADU) (Updated 06/01/2026), last read October 22, 2026. An address’s own page checks its lot for slopes, flood zones and critical areas.