ADU Permits in Kirkland

Rules for detached (DADU) and attached (AADU) accessory dwelling units in Kirkland, King County.

Free lookup. We’ll resolve your zoning, setbacks, and which ADU types are allowed on your specific parcel.

Choose an ADU type for your parcel

State law (RCW 36.70A.681) requires Kirkland to allow two ADUs on a lot in a single-family zone — one attached and one detached, two attached, or two detached — except on lots with critical areas or their buffers. An address’s own page checks its lot’s zoning.

Kirkland permit-process facts

Permit department

Submit through the Kirkland permit portal.

Permit portal

ADU permit fees

Set by the Kirkland fee schedule.

Fee schedule

Kirkland prices an ADU's building permit on the value of the work: $639 for the first $25,000 plus $17.46 for each $1,000 more up to $50,000, $1,048 for the first $50,000 plus $10.27 for each $1,000 more up to $100,000, and $1,620 for the first $100,000 plus $8.22 for each $1,000 more up to $1,000,000. Plan review is 65% of that fee, the energy code fee $101 plus 1 cent per square foot of heated or cooled space, and the state building code fee $6.50. For new construction, the plumbing and mechanical permits are each 8% of the building permit fee and the City's electrical permit 9.5%. An ADU over 800 square feet pays impact fees per square foot: park $2.59, fire $0.38 of conditioned floor area, and transportation $2.26 (July-December 2026). A separate planning review of the ADU, $634, is not required when it is reviewed with the building permit. A 3.5% technology fee is added to the City's permit and plan review fees (Kirkland Building Services Fees, 2026). Apply via mybuildingpermit.com.

Review timeline

Measured, detached ADU: half issued within 217 days of application, 80% within 33530 permits, last 12 months. Source: City of Kirkland single-family building permits (type BSF) on MyBuildingPermit.com.

HB 1337 conformance

Kirkland permits at least two ADUs per single-family lot, with no owner-occupancy requirement and parking limits that respect the HB 1337 ceilings.

Building code: 2021 IBC w/ WA amendments · Residential: 2021 IRC w/ WA amendments · Energy (WSEC): 2021 WSEC

These are Kirkland’s ADU rules as Kolmo reads them; an address’s own page adds its setbacks, easements and critical-area buffers. Source: kirklandwa.gov, last verified 2026-05-29.

ADU permits in Kirkland — FAQ

Does Kirkland allow detached ADUs (DADUs)?

Yes. Washington's HB 1337 (RCW 36.70A.681) requires Kirkland to allow at least two accessory dwelling units on a lot in a single-family zone within the urban growth area, attached or detached in any combination, except on lots with critical areas or their buffers.

What is the maximum ADU size in Kirkland?

State law bars a city from setting a maximum ADU size below 1,000 sq ft of gross floor area (RCW 36.70A.681(1)(f)). Kirkland's own maximum may be higher — the per-parcel page shows it with the city's code citation.

How long does it actually take to get a detached ADU permit in Kirkland?

30 permits with plan review issued in the last 12 months: half were issued within 217 days of application and 80% within 335. Measured by Kolmo from City of Kirkland single-family building permits (type BSF) on MyBuildingPermit.com.