Attached ADU (AADU) Permits in Mercer Island

An ADU built inside or attached to the primary residence — basement conversion, garage conversion, or bump-out addition. Lower cost; constrained by the primary footprint.

Free lookup: your lot’s zoning and setbacks, with an attached ADU placed on it to move and turn.

Permit fees in Mercer Island

Set by the Mercer Island fee schedule.

Mercer Island fee schedule

Phase A Land Use fee per MI Fee Schedule (Type II Land Use Review line). Phase B Building permit fee is valuation-based: ~$2,100 building + ~$1,365 plan review (65%) + WA BCC $6.50 + per-fixture plumbing/mech fees at $280k valuation. Impact fees (school, transportation, parks) ~$5,000-$15,000 BEFORE HB 1337's 50% ADU cap — confirm MI has updated its schedule.

Review timeline

Typical: 30–90 business days

What Mercer Island asks for with an attached ADU

Every application (10)

  • Building Permit Application, through the Permit Submittal Portal
  • Accessory Dwelling Unit land use application (LU-16), with the Development Application, narrative and code compliance matrix
  • Title report, less than 30 days old (Affidavit of Ownership where it does not show ownership)
  • Affidavit of Agent Authority, notarized (where someone other than the owner applies)
  • Residential Code Coversheet (SF1), applicant sections completed
  • Water Meter Sizing Worksheet, every fixture in the house and the ADU
  • 2026 Fire Area and Valuation Form: sprinklers at 50% of the house's value, a monitored fire alarm at 10-49% with a fire flow, hydrant or access deficiency
  • Site plan
  • Tree Inventory and Replacement Submittal Information Form
  • Floor plan

Where the lot or the work calls for it

Where the ADU adds onto the house or changes its outside walls, windows or roof

  • Site Development Worksheet
  • Typical building / wall section
  • Major materials schedule

Where the ADU adds onto the house or changes its structure

  • Boundary and topographic survey, by a Washington licensed land surveyor
  • Tree plan, with the tree retention summary
  • Utility plan

Where the work changes the outside walls, windows or roof

  • Building elevations N/S/E/W
  • Glazing + door schedule (NFRC U-factor / SHGC)
  • WSEC energy compliance and the selected energy credits, on the plans
  • Energy Code Worksheet: 2021 WSEC-R Single Family Prescriptive Worksheet (WSU)

Where the ADU adds onto the house or changes its structure, and where the lot has a steep slope, is in a landslide hazard area or is in a seismic hazard area

  • Structural calculations, stamped by a Washington professional engineer

Each where the condition beside it holds

  • Intake Screening Request Form, where the unit adds 500 sq ft of footprint or impervious surface, or alters a critical area
  • Arborist report, where a tree is removed or the work is within a dripline
  • Stormwater review: Small Project Stormwater Site Plan / Report, drainage plan and TESC plan (net 500 sq ft of new impervious surface)
  • Construction Management Plan, where the gross floor area overall exceeds 6,000 sq ft

From the city’s own documents: City of Mercer Island — Intake Screening Request Form (updated 1-2025) · City of Mercer Island — How to Upload Your Submittal · City of Mercer Island — Accessory Dwelling Unit, LU-16 (1/26) and 10 more, last read October 21, 2026. An address’s own page checks its lot for slopes, flood zones and critical areas.

The other 10 documents

AADU-specific requirements

  • Egress on every bedroom — IRC R310 net clear opening ≥5.7 sf; sill ≤44″ from floor.
  • Smoke + CO alarms — interconnected throughout primary + AADU per IRC R314/R315.
  • 1-hr separation — required between AADU and primary in some cases; otherwise a continuous draft stop.
  • Independent kitchen + bath — full plumbing + cooking provision in the AADU.
  • Address or unit number — the city or county assigns addresses; ask the permit center whether the unit gets its own.